Roseland Clubhouse

Secondary Logo_Full Color

This project includes the construction of a new clubhouse at Roseland Park for the community and be available as a rentable space. The new building will provide barrier free access and will be relocated to the west side of the park near the volleyball court and splash pad.

BUDGET: $1,088,800.00

WHY is this project needed: The original clubhouse, built in the 1960's, had been flooded 3 times and was underwater for a week after Hurricane Harvey. It was also located too close to Cedar Bayou, so it has been relocated to the west side, where it will have a higher elevation. This building provided a key quality of life for city residents, hosting birthday parties and reunions. The goal is to bring this back into the City of Baytown and provide an additional rental space for residents to utilize and enjoy.

HOW LONG will this project take: This project will begin construction in December 2021. 

WHAT are the project improvements: The clubhouse will include a catering kitchen, indoor and outdoor seating areas, and restrooms.


Roseland Park Project Updates

Interior of the Clubhouse at Roseland Park. Large open room with a large screen TV and windowsOctober 30, 2023 update

The Clubhouse at Roseland Park is complete! Rental availability will start in November. 
For more information, visit https://baytown.org/872/Facility-Rentals

Workers with tools standing on ladders installing acoustic paneling.

October 4, 2023 update

Parks teams are installing acoustic panels at the Roseland Clubhouse.

August 24, 2023 update

Council is set to close the construction phase of Roseland clubhouse on the August 24th agenda.

New glass garage doors on the deck of the Roseland Park clubhouse.June 12, 2023 update

New garage doors have been placed.

Roseland Clubhouse interior with new flooring and lightsApril 11, 2023 update

Interior work on the Roseland Clubhouse continues including flooring, lighting, and electrical.

Safety railing has begun being placed along the exterior of the Clubhouse February 28, 2023 Update

Safety railing has begun being placed along the exterior of the Clubhouse porch.

Roseland :The wiring process of the building has begun and the outside lights are now on January 20, 2023 update

The wiring process of the building has begun and the outside lights are now on.

Roseland Parks Projects Update: The sink area has been installedJanuary 5, 2023

The sinks have been installed into the kitchen area. 

Roseland Park Project: The garage windows and brick have been placedDecember 21, 2022

The garage windows and brick have been placed to near the completion of the exterior look.  

Roseland Park Project: Sheetrock installation process has startedNovember 15, 2022

Sheetrock installation process has started.

Roseland Parks Projects Updates. The front porch with the painted exterior has progressed.October 1, 2022

The front porch with the painted exterior has progressed.

4September 17, 2022

The Roseland Clubhouse walls are in place.

Roseland Parks Projects Updates. The support beams, walls, and the roof has gone upAugust 17, 2022

The support beams, walls, and the roof has gone up for the Roseland Clubhouse.

2July 18, 2022

The foundation forms have been removed and the site is ready for the building phase.

ROSELAND Parks Projects Updates. The foundation has been set

July 2, 2022 

The foundation has been set at the appropriate level for the floodplain.